A 58-apartment ICF scheme whose structure went up 35 to 40% faster than a traditional frame, taking three to four months off the overall programme.
Project overview
An ambitious project called for Amvic ICF.
58 apartments over five storeys, designed to stay below the Higher-Risk Building (HRB) threshold. The site was acquired through a land sourcer and moved smoothly through planning. The developer chose Amvic ICF for its ability to deliver a high number of units efficiently on a low-rise scheme of this size. An RC frame was previously considered, but ICF proved to be the best route. It brought speed, strong acoustic and airtightness performance and fewer trades on-site, all in a single system.
Key technical highlights
ICF system
Amvic 370 and Amvic 330 ICF blocks with a 200mm concrete core, used throughout the five-storey apartment building.
Acoustic separation and airtightness
Fitting 58 apartments into a five-storey building called for strong acoustic separation between flats alongside very good thermal and airtightness performance. ICF delivered all of this in one system, without extra layers or trades.
Fewer trades on-site
Walls, insulation and structure go in as a single system, so there were fewer separate trades to co-ordinate. The system handled the repetitive apartment layout efficiently, and its lightweight, easy-to-handle blocks made logistics and storage simpler on a tight site.
Programme-led delivery
The structure rose at a steady floor-by-floor pace, around 35 to 40% faster than a traditional frame. First fix and internal fitout began on the lower floors while the upper floors were still being built. Running those trades side by side took three to four months off the overall programme.
Outcome
The shorter programme reduced preliminaries and site overheads, but the biggest commercial gain came from development finance. Completing months earlier saved a significant amount in finance interest, which went straight to the bottom line. The building performs well, and the developer is already looking at ICF for future schemes.
Client testimonial
“The biggest benefit was speed. Saving months on the programme cut our finance costs a lot and got us to completion sooner, and the building performs very well too. We would definitely use ICF again and are already looking at it for future developments.”
Harsev Singh Randhawa, Founder, Frontier Group